Coal Gasification Scheme 2026: Subsidy & ₹37,500 Crore Financial Incentive

Introduction: Coal Gasification Scheme 2026

The Coal Gasification Scheme is India’s biggest push yet to turn coal and lignite into syngas, fuels, and chemicals. The government has approved ₹37,500 crore for it. However, the money is not a free grant. Each applicant must win a competitive round, meet strict rules, and reach set milestones.

Many people call it a coal gasification subsidy. Officially, it is a “financial incentive”. In this guide, you will learn how the financial incentive works, who can apply, and how projects are scored. Also, round 2 closes soon, so the dates matter.

What Is the Coal Gasification Scheme?

The Ministry of Coal runs the scheme. The Scheme for Promotion of Surface Coal/Lignite Gasification Projects. The Ministry conveyed the approval through an office memorandum dated 25 June 2026. The outlay is ₹37,500 crore, and it is spread over FY 2026–27 to FY 2032–33.

The scheme has three clear goals. First, it speeds up surface coal gasification. Second, it cuts imports of urea, ammonia, methanol, DME, and similar products. Finally, it supports the national target of 100 million tonnes of coal gasification by 2030.

This is not the earlier ₹8,500 crore scheme from 2024. That older scheme used a 0.4 MT minimum and a 15% cap. The new surface coal gasification scheme in India uses different rules, as shown below.

Coal Gasification Scheme Eligibility

Coal gasification project eligibility criteria are clear. First, the applicant must be a PSU, a private company, a joint venture, or a consortium of up to three companies. Next, the project must be new, based on surface coal or lignite, and located in India.

Then comes the money test. The applicant’s net worth must be more than 20% of the project cost. For a ₹10,000 crore project, that means a net worth above ₹2,000 crore.

Net worth is not reusable. If you win one project, the net worth you committed to is deducted for your next application. For example, a second project must clear the test after you subtract 20% of the first project’s cost.

The applicant must also confirm the following:

  • It is a company under Indian law or a foreign company under its home law
  • No insolvency case has been admitted against it
  • Its promoters or directors have no coal block conviction and no jail term above three years
  • It follows all applicable laws

A consortium has extra rules. The lead member must hold at least 51% of the consortium’s equity. All members must sign a joint application agreement. In addition, every member must meet the conditions above.

Coal Gasification Syngas Capacity Eligibility

The minimum capacity is 0.5 million tonnes per annum (MTPA) of clean syngas. The RFP assumes 330 operating days and a syngas density of 1.1 kg/Nm³.

Based on these inputs, our own calculation gives roughly 57,400 Nm³/hr of clean syngas. Please treat this as a quick estimate and confirm it with your technical team. Moreover, scoring points starts only above 60,000 Nm³/hr. So, a plant that barely meets the minimum earns no capacity marks.

Clean syngas also has a quality test. Hydrogen and carbon monoxide together must be at least 55% by volume. Nitrogen must not exceed 40%. Both are measured on a dry basis. If nitrogen is higher, the Ministry may decide case by case. Producer gas does not qualify as syngas.

Coal Gasification Scheme Eligible Products

Applicants choose their own downstream products. The RFP lists 22 examples, including:

  • Urea, ammonia, and ammonium nitrate
  • Methanol, ethanol, and DME
  • Synthetic natural gas and hydrogen
  • Direct Reduced Iron (DRI)
  • Diesel, gasoline, naphtha, and aviation fuel
  • Olefins, MEG, MMA, and MTBE

The list is indicative. So, you can request a new product with a written justification. However, end-use goods do not qualify. Steel from DRI, fertiliser blends, and paints are examples.

When a project makes more than one product, the incentive is worked out for each product. It is split by the share of P&M cost, and the caps apply to each product. Also, a shortfall in one product cannot be moved to another.

Coal Gasification Scheme Financial Incentive: How It Works

The coal gasification scheme financial incentive is at most 20% of the cost of plant and machinery (P&M). It is not 20% of the total project cost. This difference matters a lot.

What counts as P&M?

  • Core plant and machinery
  • Technology licence
  • Erection and installation for syngas or downstream products
  • Control rooms, cooling towers, warehouses, and support structures tied to equipment

What does not count:

  • Land and site development
  • General buildings and civil works
  • Pre-operative and financing costs, including interest during construction
  • Used, refurbished, or transferred machinery
  • Any spending before scheme approval (the RFP gives 13 May 2026)

Because of this, only new and unused equipment qualifies. In addition, the equipment must serve the project alone.

Three caps apply:

  • ₹5,000 crore for any single project
  • ₹9,000 crore for any one product, except urea and synthetic natural gas
  • ₹12,000 crore for one applicant and its group companies, across all projects

The incentive is not equity. Therefore, you cannot count it toward your own equity share for debt or financial closure. Meanwhile, you can still claim benefits under the commercial coal mining regime. You can also use schemes of other ministries and state governments. However, the Ministry of Coal will not give any other separate incentive.

How the Incentive Is Paid

The incentive comes in four equal instalments of 25% each.

  1. First: after land, environmental clearance, coal tie-up, technology licensor, EPC contractor, and financial closure
  2. Second: after the loan disbursal, 30% equity infusion, and spending of 50% or more of the incentive on P&M
  3. Third: on commissioning
  4. Fourth: after the plant reaches 50% of peak capacity over the previous 365 days

Before the first instalment, you must submit a surety bond or bank guarantee worth 25% of that instalment. Timing also matters. If commissioning slips past five years, the remaining incentive falls to 50%, then 25%. Beyond seven years, it falls to nil. Force majeure time is excluded.

Coal Gasification Scheme for Private Companies

Private companies are fully eligible. They compete on the same terms as PSUs. A sole applicant may run the project directly or through an SPV. However, a JV or consortium must form an SPV with the same shareholding as in the application.

If your ultimate owners are in India, you must obtain the required approvals before the Letter of Award. Also, you must hold at least 51% of the equity during the lock-in period. Any transfer needs prior approval from the Ministry.

Why Work with a Coal Gasification Scheme Consultant in India

The rules are detailed, and the scoring is competitive. A single wrong number in the P&M cost can change your rank. Therefore, many firms hire a coal gasification scheme consultant in India before they apply.

At Finraja Consultancy Pvt Ltd, we work as a subsidy consultancy. We help you:

  • Check eligibility and net worth headroom
  • Separate eligible P&M cost from excluded costs
  • Model the best incentive percentage for scoring
  • Prepare the PFR or DPR and the application set
  • Plan milestone claims and compliance

Contact Finraja Consultancy today for a free eligibility review before the Round 2 deadline.

Frequently Asked Questions

What is the coal gasification subsidy amount?

The incentive is up to 20% of P&M cost. It is capped at ₹5,000 crore per project.

Can a private company apply?

Yes. Private companies, PSUs, JVs, and consortiums of up to three companies can apply.

What is the minimum plant size?

The minimum is 0.5 MTPA in clean syngas terms.

Conclusion

The Coal Gasification Scheme offers a rare chance to fund large projects. However, success depends on clean numbers, strong net worth, and timely filing. So, start your review now, and speak with an expert before you file.

Call us now: +91 9373114747 or visit finraja.com/contact for quick assistance.

Share post:

Leave a Reply

Registration Form

Fill out the form below, and we will be in touch shortly.

Registration Form

Fill out the form below, and we will be in touch shortly.